ATHLETIC FACILITIES – UPGRADES & RENOVATION Construction Schedule: Completed Fall 2005 Funding Source(s): Redevelopment Funds |
|
Description: The outdoor athletic facilities at Beginning in the Spring of 2004, these facilities will be improved by implementing the following projects:
|
|
· upgrade of the existing football field to synthetic turf, complete · renovation of the existing track, complete · upgrade of the existing baseball field to synthetic turf, complete · new restrooms, storage and batting cage structures, complete · infrastructure for sport field lighting, complete
|
· renovation of stadium bleachers, in process · installation of a new press box, in process · renovation of the field throwing area, in process · accessibility upgrades to all fields from parking areas, in process
|