From: Martinez, Diane
Sent: Tuesday, June 06, 2006 6:36 PM
To: CSM Employees
Cc: Anchartechahar, Roger; Nielsen, Elisabeth
Subject: CONSTRUCTION NOTICE - BLDG 8 & LOT 3

 

 

 

PROJECT NAME:

 

CSM Building 8 Energy Efficiency & Roofing Upgrades

 

 

 

PROJECT DESCRIPTION:

 

Two new HVAC units and enclosures will be installed over the small gymnasium in Building 8.

 

 

 

SCHEDULE:

 

6/8/2006  -  7 AM -2 PM

 

 

 

CAMPUS IMPACT:

 

Two new HVAC units will be loaded over and on to the small gymnasium area.  There will be no access through the Lot 3A level entry area of Building 8 during this time. Access to Building 8 will be through the campus side (North) entry.

 

Lot 3A will be closed off to all vehicle access. A large crane with other construction vehicles will be staged in Lot 3A and 3.

 

Please exercise caution should you need to be in the area.

 

 

 

PROJECT CONTACT:

 

Please direct any questions or concerns related to this project to:

 

 

 

NAME:

 

Roger Anchartechahar

EMAIL:

 

anchartechaharr@smccd.net

TELEPHONE:

 

650-378-7336

 

 

 

For more information regarding the Capital Improvement Program, please visit the Campus Construction Update page at:   www.collegeofsanmateo.edu/construction

 

 

Diane Martinez

Facilities Manager

College of San Mateo

(650) 574-6577

(650) 574-6203