spacer
smcccd
The Facilities at SMCCCD
Work Request
User ID: @smccd.edu


 

 

 

 

 

Skyline College Electrical Infrastructure Replacement / Load Center 2 Project
Replace this with Building Photo
Photos
Project Description:

This project provides for the design and construction of an above ground pad mounted electrical Load Center to replace the existing underground Load Center #2 at Skyline College. There are four existing Load Centers at Skyline College: Load Center #2 is in an underground vault while the others are located indoors. Each load center includes; 12,000 volt switches, a transformer and a main switchboard that distributes power at the proper voltage, usually 480 volts, to building panel-boards and motor control centers. All of the main switchboards at Skyline are old and the equipment is generally obsolete, however, Load Center #2 is especially deficient and has deteriorated to the point where failures are increasingly common, occurring several times a year. The equipment and cabling has been subject to moisture in the form of standing water, is in extremely poor condition and requires immediate replacement. Standing water in the underground vault is dangerous for staff servicing this equipment and the replacement will be an appropriately configured outdoor unit. Personnel egress and work space do not meet current Codes for electrical safety in the workplace. For all of these reasons it has been determined that a complete replacement of Load Center #2 is warranted.

Project Benefits:

In order to adequately address the deficiencies identified with the existing electrical infrastructure system, the infrastructure replacement will address the following:

  • Upgrade Load Center 2 switchgear and provide new related code-compliant underground distribution system
  • Address critical life safety issues
  • Correct code deficiencies
  • Protect property and equipment from damage that couldresult from infrastructure failure
  • Mitigate risk of disruption of educational program delivery due to infrastructure failure
  • Correct deficiencies in the most cost effective manner
Schedule
  • Design Phase:  Jan 2010 – March 2011
  • Bidding:  March 2011 – April 2011
  • Construction: June 2011 – Jan 2012
  • Completion: Jan 2012
  • Project close-out: Feb 2012
Status:

Complete

Project Manager: Drew Bagdasarian
Telephone: p: 415-397-4430 c:415-515-6840
E-Mail dbagdasarian@drbassociates.com
Project Assistant: Stephen MacMillan
Telephone: p: 415-397-4430 c: 415-846-7943
E-Mail smacmillan@drbassociates.com

Architect:

WRNS Studio
General Contractor: Not Yet Selected
Funding Source(s): Measure A General Obligation Bonds

 

Facilities Planning & Operations
Phone: (650) 574-6512
Fax: (650) 574-6574

San Mateo County Community College District
3401 CSM Drive
San Mateo CA 94402

spacer   
   
spacer
spacer

Copyright 2011 © San Mateo County Community College District. All rights reserved.
Questions? Contact the Webmaster